New Prescott South At 40% + Completion

Tools

By Ward Norris

As of February 4, the project was 45 % complete and roofs are on two of the five buildings.

As you can see in the photo, the middle school’s gym has the brickwork done on it.

The second floors are on the elementary and middle school wings, and the walls in the center part of the building are now starting to go up.

Miller commented that the rain and snow has slowed the project some, but the crews are staying at it as fast as mother nature allows.